Cable Pulling – Earls Court

Year: 2017
Client: Track Partnership
Cost: Circa £85K

Earls Court to Triangle Sidings was a 2-phase cable pull totalling 1100m of 50mm 3-core cable being pulled and secured on new and existing high and low level CRMS for points 8AB.

The high level cable posed its own set of challenges with the majority being over 4m from track level and OTX’s spanning all 4 roads.

Additional installations for these works included core hole drilling, Cable troughing, 2 new hardstands to house the Isolation Transformers, Points Control Kiosk, support frames for Monitoring Equipment and Schneider Boxes.